8, Jalan 1, Taman Sri Ukay Off Jalan Ulu Kelang, 68000, Ampang Selangor D.E. Malaysia
[ t ] 603-4257 1966, 603-4257 1948 [ f ] 603-4256 1005, 603-4256 9330 [ email ] trhy@trhamzahyeang.com
::
 
 
 
 
   
Project Name :
MENARA UMNO, Pulau Pinang

Owner:
South East Asia Development Corporation Berhad
Komplek Kewangan, Jalan Raja Chulan, Kuala Lumpur


Areas:
Total gross area (including carparking) = 10,900 sq.m.
Total net area = 8,191.98 sq.m.
Nos. of carpark bays: 94 bays

Nos. of storeys:
21-storeys

Location:
Jalan Macalister, Penang, Malaysia

Date Start:
1995

Completion Date:
1998 (March)

Site Area:
1,920 sq.m.

Plot Ratio:
1 : 5.5

   
Design Features
The site has an area of about half acre, and is centrally located at the junction of Jalan Macalister and Jalan Zainal Abidin in Pulau Pinang. It is within 5 minutes walking distance to KOMTAR in Penang Road.

The proposed tower on this site is 21-storeys and contains spaces for Banking Hall at the ground floor and at Level 1 and an Auditorium for meetings and assemblies at Level 6. The Auditorium is also accessible by a separate external staircase. Above this are 14 floors of office space.

The building's design features are as follows:

All office floors (although designed to be air-conditioned) can be naturally- ventilated. For example, no desk location (within each typical floor) is more than 6.5 metres (c. 20 feet) away from an openable-window to enable users to receive natural sunlight and ventilation.
The building has wind wing-walls to direct wind to special balconies zone that serve as pockets with "air-locks" (having adjustable doors and panels to control the percentage of openable windows) for natural ventilation. This building is probably the first high-rise office that uses wind as natural ventilation for creating comfort conditions inside the building. Other claims of 'natural ventilation' in high-rise towers, use natural ventilation simply as a source of fresh air-supply to the interior and not for internal comfort. For internal comfort as in this building, a higher level of air-change per hour is required. Here, we tried to introduce natural ventilation at point of entry (rather than create suction at the leeward side). To create pressure at the inlet, a system of 'wing-walls' to "catch" the wind from a range of likely directions. The wing-walls are attached to a balcony-device with full-height sliding-doors. The placements of the wing-walls and air-locks within the floor- plate are based on the architect's assessment from the locality's wind-data. The wing-wall cum air-lock device is of course experimental, and site verification with CFD analysis indicate that this device worked reasonably well. Experiences from the project, would enable the architect to further develop the device for other projects.
The building was originally designed for tenants to install their own split- unit air-conditioning as it was perceived that the poor rental rates (in Penang) did not justify the installation of a central system. However a central air- conditioning system was subsequently installed. The design for natural ventilation then provided a back-up system to the building (in the event of power failure).
All the lift lobbies, staircases and toilets also have natural sunlight and ventilation making the building safe to use (i.e. naturally-lit stairs and lobbies in the event of power failure or other emergencies) and are also low-energy to operate.
Sun-shading is solar oriented.
 
Energy Consumption
The cooling load of the building is 6,000,773 BTU (500 RT).
The air-conditioning consumption is 126 kWhr/sq.m./annum.
The total energy consumption of the building is 244 kWhr/sq.m./annum
The energy consumption, if naturally ventilated (i.e. without air-conditioning) is 118 kWhr/sq.m./annum. (Source: Ranhill Bersekutu Sdn Bhd)
 
Structure & Sub-structure
A total of four test boreholes were conducted, each to a depth of about 64m for the sub-structure design. Generally, these borelogs indicate the site to be underlain by successive layers of very soft to soft clay, followed by medium stiff to very stiff silt and silty sand. Ground water table is generally between 2.7m to 3.5m below Ground level.

Column loadings vary from 3,200 Tonnes to 1,800 Tonnes for the widely -spaced columns. For the more closely spaced columns, the loading is about 740 Tonnes.

In the selection of foundation for the structure, shallow foundation like pad footing and raft was considered to be obviously not suitable in view of very poor soil (N - value of 3) to a depth of 9m below Ground level. Bored piling was not adopted in consideration of high water table with silty sand and low N-values at the upper layers. The requirements of long length of steel casings associated with boring in such soil to prevent collapse of bore holes would not merit value engineering decision.

For such soil condition and medium range column loadings, it was considered most appropriate to adopt driven reinforced concrete piles. Further reasons to justify the use of driven r.c. piles are that they are economical (especially, when compared to steel piles) and could be installed relatively quickly. Information on the piles used are as follows:

Size = 400mm x 400mm, with welded joint
Grade of Concrete = G45
Driven Length = Average 55m
Working load =
185 Tonnes
Maximum No. of piles/column =
18

Essentially, these piles are skin friction piles which mobilise the good soil resistance properties at depth of 30 to 55m.

The idealised structure consists of moment resisting frames coupled to a shear wall. Horizontal and vertical r.c. members are rigidly connected together in a planar grid form which resists lateral wind loads primarily through the flexural stiffness of the members. This type of structural system is efficient to enhance the sway serviceability performance of the building. The structural analysis was carried out using the computer software STAAD-III, with the appropriate gravity loads and wind loads, derived from a basic wind speed of 35.8m/s (80mph).

The maximum computed horizontal deflection of 98mm, is well within the deflection limit of H/500 (85m/500 = 170mm).

The building was designed for conventional r.c. beam and slab construction which is most economical for such medium height range. Furthermore, many local builders were able to tender for this job. The quantity of concrete (G30) and steel reinforcement (Fy = 460 Mpa) used for the superstructure are as follows:

Concrete : 5,696 m3
Steel: 1,195 Tonnes

In order to achieve an early hand over of the lift r.c. wall for lift installation, the contractor adopted the “Jump Form” construction with a construction cycle time of 8 days for 3.9m height of wall. With this method, the contractor was able to complete the r.c. wall construction 3 months ahead of the other areas which was constructed using normal steel and timber framework.

The entire project, including piling works, was completed in 22 months.

 
Project Team :  
Principal-in-charge:
Dr. Ken Yeang

Design Architects:
Tim Mellor
Ang Chee Cheong
Project Architect:
Shamsul Baharin
Mohd Pital Maarof

Design Development Architects:
Tim Mellor
Azman Che Mat
Jason Ng
Mike Jamieson
Richard Coutts
   
LIST OF CONSULTANTS AND CONTRACTORS
 
canopy plan
shading details section
typical level
menara umno section details
roof top canopy
menara umno west elevation
detail of wind pocket
menara umno south elevation
level 1
roof canopy plans
 
top
 
 
Copyright © T.R.Hamzah Yeang Sdn. Bhd. International ( 41743A).All rights reserved.